Contact: Amy Miller, EPA Press Office (617-918-1042)
For Immediate Release: January 25, 2001; Release # 01-01-09
BOSTON - The U.S. Environmental Protection Agency today announced the agency's plan for the next phase of cleanup at the Centredale Manor Restoration Project in North Providence R.I. This cleanup plan addresses the shores of the Woonasquatucket River between Centredale Manor and Lymansville Dam. The $2.6 million cleanup plan, slated to begin this summer, also calls for the restoration of Allendale Dam.
|
Additional Information |
||
| Centredale Manor NPL Fact Sheet Woonasquatucket Web Site | ||
The selected cleanup plan, first proposed to the public last fall as part of an Engineering Evaluation/Cost Analysis (EE/CA), involves the excavation of about 2,500 cubic yards of dioxin-contaminated sediments and bank soils to meet EPA's cleanup criteria. The material will be excavated and transported off-site for treatment.
EPA plans to request that potentially responsible parties at the site voluntarily perform or fund the cleanup activities.
"This approval is a major milestone in the cleanup of the Woonasquatucket River," said Ira Leighton, acting regional administrator of EPA's New England Office. "For the first time, we'll be removing contaminated material from the site."
"This cleanup plan is an important step towards the community's goal of once again making the Woonasquatucket River fishable and swimmable," Senator Lincoln Chafee said. "I commend both the EPA for its work in cleaning up the site, as well as the people living along the Woonasquatucket who have taken such an active and vital interest in this project. I look forward to working with everyone involved to ensure this project moves forward."
"The Department is pleased that the cleanup at the Centredale Manor Site is continuing to move forward. This removal action will significantly reduce risks to the residents and contribute to our long-term goal of making the Woonasquatucket River fully accessible for fishing and swimming," said Jan Reitsma, director of the Rhode Island Department of Environmental Management.
"I commend the EPA for its diligent response to cleaning up this site," Congressman Kennedy said. "Less than one year after placing this restoration project on the National Priorities List of hazardous waste sites, the EPA already has an ambitious plan of action in place."
"This is good news for the environment and the health and safety of communities downstream from Centredale Manor and the Allendale Dam. I look forward to the implementation of the final clean up plan as soon as possible," said Senator Jack Reed.
Key elements of the cleanup plan include:
Field work for this portion of the cleanup project is expected to begin this summer and is expected to be finished by next summer. EPA will make design plans available and will meet with affected property owners prior to beginning the work.
Information on EPA's selected remedy is available at the following locations:
Salvatore Mancini Union Free Library
1810 Mineral Spring Ave.
North Providence, RI
Marian J. Mohr Library
1 Memorial Ave.
Johnston, RI
EPA New England
Records Center
1 Congress St.
Boston, MA 02203
For more information on dioxin, go to